New payment laws in California and Florida: What contractors must document to avoid penalties in 2026

workers jobsite

The 2026 era of construction supplier and subcontractor payment protection in California and Florida has seen new beginnings. The Golden State’s Fair Payment Act now applies to private construction contracts signed on or after Jan. 1, while the Sunshine State’s Prohibition Against Nonpayment took effect on July 1. Erring prime contractors in California are subject to interest payments, and violators in Florida may face disciplinary proceedings against their professional licenses. If your license is revoked, you could be liable for criminal penalties if you continue working in the industry.

The consequences for contractors deemed noncompliant can be damaging financially and reputationally. Establishing legitimate good-faith disputes is key to justifying withholding of payments. Learn how to use proper construction payment dispute documentation to defend your organization against claims.

New California law and added subcontractor payment protection

The main difference between the old and new California contractor payment laws is the right for subcontractors to recover interest on disputed amounts. Under the Fair Payment Act, the subcontractor doesn’t have to prove that the prime contractor didn’t act in good faith in withholding disputed funds. It enables the claimant to collect interest at the penalty rate of 2% per month, or 24% per annum, which also applies to undisputed amounts later deemed due.

The California Business and Professions Code Section 7108.5 requires prime contractors to pay subcontractors within seven days after receiving each progress payment. You should pay the third parties you hire for the work they performed within this window, unless all parties agreed to a different time frame in writing.

California's construction payment dispute documentation requirements

Although the new law provides stronger subcontractor payment protections, it also recognizes that legitimate construction disputes justify withholding of payments when backed by proper documents.

Examples of good-faith disputes include:

  • Defective workmanship
  • Deficient contractual performance
  • Disputed change-order work
  • Incomplete document submission
  • Pending liability issues
  • Unresolved quantity or price disagreements
  • Unsatisfied contractual milestones
  • Unsettled back charges

A 2024 survey from the Associated General Contractors of America found that about 70% of risk managers reported an increase in subcontractor distress or defaults compared to the previous year. Given this trend, you should train your field workers to collect data as thoroughly as possible to support good-faith disputes. Section 7108.5 of the California Business and Professions Code permits you to legally withhold up to 150% of the amount being disputed, and you may successfully assert legitimate back charges when contractually entitled.

The range of justifications for withholding subcontractor payments is broad, so you need to gather diverse evidence to back up your counterclaims, which is where accurate documentation systems can support compliance and refute disputes. Daily reports, progress photos, timestamped work records and change orders tracking are essential documents your team should keep in a centralized system.

Moreover, use a field management software solution for data collection and recordkeeping, which should reduce your compliance risk. This tool streamlines and automates documentation at every turn. It enables your company to create digital trails when assigning, tracking and evaluating your subcontractors’ tasks. Centralizing construction task management helps ensure relevant stakeholders receive vital instructions, promotes accountability and prevents incomplete closeout documentation.

Construction productivity thieves blogimage

Florida’s 2026 law protects subcontractors and suppliers from late payments

Prohibition Against Nonpayment, or Section 489.1295 of the Florida Statutes, requires licensed contractors to compensate subcontractors for the services they perform and suppliers for the materials they deliver within 45 days of being paid or in accordance with the terms of the contract.

If you knowingly or willfully violate this requirement, the professional license tied to your organization will be subject to disciplinary proceedings. The Construction Industry Licensing Board may take actions against the registrant or certificate holder.

These include:

  • Reprimanding or placing the licensee on probation.
  • Demanding financial restitution for financial harm.
  • Imposing an administrative fine per violation.

Florida's 2026 construction payment dispute documentation requirements

This 2026 Florida subcontractor and supplier payment law’s exemption applies to contractors with existing bona fide disputes regarding the claimed amounts. While the statute doesn’t explicitly define what constitutes bona fide disputes, you should treat the term as genuine, good-faith disagreements over whether the amount is actually owed to justify the withholding.

Careful documentation is essential for defending your organization against allegations of nonpayment when a construction payment dispute arises. Your team should gather detailed field work data to prove your reasonable justification for withholding the funds, such as subpar job performance, legitimate back charges and missing closeout documentation.

Every bona fide dispute is different and merits unique documentary evidence. Use cloud-based field management software solutions to create daily logs in minutes by using templates that track the progress of tasks, facilitate requests for information, generate photo and visual records with metadata, verify workflows and support offline inspections.

Furthermore, specifying payment terms in the contract matters. The 2026 Florida contractor payment law places considerable weight on the language in the documents, especially regarding the pay-when-paid or pay-if-paid clauses, which sound similar and can be confusing.

Prioritize field work documentation to reduce compliance risk

Adjusting to the 2026 California and Florida contractor payment laws is easier with the right technology and mindset. Investing in robust field management software and seeking expert legal advice are crucial for countering disputes and protecting against costly legal repercussions.

Frequently asked questions about California and Florida payment laws

Under California Business and Professions Code Section 7108.5, prime contractors or subcontractors generally must pay subcontractors within seven days of receiving each progress payment, unless a different timeframe has been agreed to in writing. A good-faith dispute can allow withholding of up to 150% of the disputed amount.

Florida Statute 489.1295 provides an exception when there is a bona fide dispute regarding the amount due. Contractors should maintain clear records supporting why a payment was withheld, including relevant field documentation, change orders, photos, daily reports and contractual records.

Contractors should maintain detailed records such as daily reports, progress photos, timestamped work records, change orders, RFIs, task histories and closeout documentation. Centralizing these records can make it easier to demonstrate what work was completed, identify deficiencies and support the basis for a payment dispute.

construction jobs

Rose Morrison

Rose Morrison is the managing editor at Renovated and an experienced writer with over seven years of experience in construction and design. She focuses on sustainable practices and innovative technologies, including construction management software. Growing up in a family of contractors gave her hands-on experience in the built environment. This fueled her passion for efficient techniques and eco-friendly solutions. She delivers valuable insights and practical tips for construction professionals looking to optimize projects with the latest software.

Get started now

Field service management software for construction

4,000,000+ projects worldwide

Helping the largest construction companies in the world more easily manage their job sites.

Graham UKEllisDonClark ConstructionBuiltClimatec logoBrookfieldCougnaudWebcorJohnson ControlsMorguardBockmon & WoodySutter HealthColt BuildersSpeller MetcalfeGraham