Firestopping documentation requirements: What UK contractors must record on every job

Firestopping-documentation-requirements-uk-contractors

The principal contractor asks for proof of what went in before the dryliner closed the shaft on the fourth floor. The photos are on someone's phone. The product reference is in a delivery note in the van. Nobody can confirm which tested system was used, and nothing links the penetration seal to an installer or a sign-off.

That documentation gap matters. Under the Building Safety Act 2022 framework, prescribed fire-safety information for higher-risk buildings sits within the golden thread — the digital record that connects each seal to the tested system, installer, location, photos, and inspection approval. Without it, even well-installed work is harder to verify at handover.

For higher-risk buildings in England, the golden thread is a legal requirement. On other projects, the same record structure is industry best-practice to show that passive fire protection documentation matches tested specifications and is properly handed over.

What this article covers

  • Higher-risk buildings need digital golden-thread records, and the same evidence structure helps other projects prove installations match tested specifications.
  • A firestop entry that satisfies golden-thread requirements links the tested system, exact location, photos, installer identity, and independent sign-off in one traceable record.
  • Responsibility moves from design into construction and occupation, so each duty holder needs usable evidence at the right stage.
  • Paper files and standalone spreadsheets make structured, searchable, long-term golden-thread information harder to maintain.
  • Field teams can build records on site by pinning penetrations, capturing products and photos, tagging seals, and exporting reports.
  • The digital golden thread is a legal requirement for higher-risk buildings in England; the same evidence discipline is industry best- practice everywhere else.
  • The strongest handover record is captured at the firestop, before close-in, and kept ready for inspection or audit.

For higher-risk buildings, industry practice for meeting golden-thread requirements ties a firestop record to a tested system, an exact location, photo evidence, an identified installer, and an independent sign-off in a single traceable entry.

A higher-risk building under section 65 of the Act is a building in England that is at least 18 metres tall or has at least seven storeys, and contains at least two residential units. St George Wharf Tower in Vauxhall, London is a clear example: at 181 metres and more than 50 storeys with 223 residential flats, it clears both thresholds several times over. For these buildings, the golden thread must be stored digitally, and the record runs from design through the entire life of the building.

For passive fire protection, the record needs to show what was installed, to what specification, using which products, and what evidence proves correct installation before anything is covered or made inaccessible. A defensible record should connect product specification, test evidence, purchase records, delivery notes, photos taken as work proceeds, and inspection evidence. It also needs traceability to the product, manufacturer, tested system, certificate, and physical installation evidence.

This record discipline also matters beyond higher-risk buildings. While the statutory digital golden thread applies specifically to higher-risk buildings, the 2025 amendments to Approved Document B explicitly refer to passive fire safety documentation, including compartmentation, fire-separating elements, fire-resisting construction, and cavity barriers. Project teams across all building types should expect each penetration to need a traceable, digital, pre-close-in record.

Webinar-Project Management for General Contractors

What counts as compliant firestopping documentation

For higher-risk buildings, a compliant firestop record ties a tested system, an exact location, photo evidence, an identified installer, and an independent sign-off into a single traceable entry. Firestop records need to connect to the drawings, installed systems, competent installation, and handover evidence. Miss any one of those and the record is open to challenge.

The tested system and product installed

The record must reference the complete tested system. Firestopping needs to be installed as a tested detail — the product, substrate type, service diameter, backing materials, and orientation must all match the manufacturer's fire test evidence or third-party certification.

That means capturing the tested detail reference, the product name and manufacturer, delivery-note or batch traceability, and the third-party certificate of conformity. In practice, that reference is a specific document: Hilti's CFS-S ACR firestop acrylic sealant, for example, carries European Technical Approval ETA-10/0292, scoped specifically to penetration seals. Records should show the relevant third-party product certification and test evidence, with BS EN 1366-3:2021+A1:2024 covering fire resistance tests for penetration seals.

One rule that has to make it into the record: products from different manufacturers should not be mixed in the same opening unless there is clear test evidence to substantiate it.

The exact location of every penetration

Every seal needs a unique reference and a precise location tied back to the construction drawings. Records should tie each penetration to floor, zone, wall, and element references so it can be found and checked against the right detail.

In practice that means a unique reference number per penetration, plus the floor, zone, and element reference so the record can be found, audited, and used for future remedial work without anyone guessing which seal is which.

Photo evidence before, during, and after

Photographs are the load-bearing proof in the whole record, and they have to be taken before the seal is closed in. A complete record of all installations should support the certificate of completion and inspection process, so walk-through visual checks during installation matter as much as the final shot.

A documented installation record should capture pre-close-in and completion photographs, product specifications including named components, and verification of the intended fire resistance period. Without that photo trail, the record cannot prove what was installed inside the wall, floor, or shaft once it has been covered.

Who installed it, when, and to which specification

The record should name the individual installer, the date, and confirm the certification of the company they work for. Service penetration seals should be installed by operatives who are third-party certified by a scheme such as FIRAS, LPCB, or IFC.

A defensible record makes two distinct certifications clear. The product or system can carry third-party product certification, and the installer company can hold third-party installer certification under a UKAS-accredited scheme. The point is to prove both that the system was suitable for the opening and that the company installing it was certified to do the work.

Inspection, sign-off, and approval

The sign-off has to stand apart from the installer's own record. At handover, the evidence should include both the installer's record and a separate approval — the record needs to show installation and sign-off as distinct steps.

Each inspection should be recorded so it can be reviewed and audited later. Golden thread information should be stored in a structured way so people can find, update, and extract the right information. That means the inspection outcome, date, sign-off, and supporting photos need to sit with the seal record rather than in a separate folder or inbox.

Who is responsible for firestopping records

Responsibility for firestopping records passes down the chain and continues into occupation. The Principal Designer holds the duty during the pre-construction phase, coordinating health and safety risks and ensuring the Health and Safety File is prepared. Once construction starts, the principal contractor takes over, installing to tested details, capturing evidential records, and coordinating specialist subcontractors. Take the shaft on the fourth floor from the introduction: the Principal Designer's fire strategy for that shaft carries into the Health and Safety File, the principal contractor assigns the actual sealing work to a specialist fire-protection subcontractor, and that subcontractor is the one capturing the photos, product reference, and sign-off before the dryliner closes it in.

For the fire-protection contractor on site, that duty runs through every task: product records, photo evidence, and structured sign-off processes. Product, Placement and Performance are the practical evidence that the work was carried out to the tested detail. From occupation onward, the Principal Accountable Person is responsible for keeping prescribed golden-thread information so the record remains usable after handover.

Where paper and spreadsheets fall short

Paper and spreadsheets fall short on both counts. For higher-risk buildings, records must be stored digitally. Paper alone does not meet the requirement.

Spreadsheets carry their own limits. Golden thread information should be stored in a structured way so people can find, update, and extract the right information. A spreadsheet that sits outside the structured golden-thread record makes it harder to prove who changed an entry, which certificate applied, and whether the latest version was the one used on site. For firestopping, that means weaker answers to who changed an entry, where the certificate sits, and who installed and inspected each seal.

Neither format handles longevity well. The record runs from design through occupation and across the life of the building, and the golden thread has to be maintained so building safety information can be found and used long after handover. Buildertrend vs. Procore: What each was built for (and what trade contractors actually need)

How fire-protection crews capture firestopping records on the site

The records get made where the work happens: on the plan, at the penetration, before anything is closed in. Crews that do this well build the record as they install it, so the evidence is complete and audit-ready the moment the seal goes in, so the evidence is complete and audit-ready the moment the seal goes in.

Field capture should cover three elements — the 'PPP' golden rule: Product (specification, test evidence, purchase orders, and delivery notes), Placement (photographic evidence as work proceeds), and Performance (a structured inspection plan). The practical workflow that satisfies all three runs roughly like this:

  • Pin a Fieldwire task to the exact penetration location on the floor plan
  • Capture the tested system and the products used at that firestop
  • Take before, during, and after photos directly at the seal
  • Complete a structured inspection form and get an independent sign-off
  • Export the lot into an audit-ready report at handover
  • Keep the record live after handover. Golden-thread information must stay accessible and current for the life of the building, not just archived at the point of completion.

Done in this order, the record is built as the work goes in rather than reconstructed afterward from photos on a phone and a delivery note in the van.

Fieldwire by Hilti supports that firestop workflow. The app gives installers plan viewing with automatic version control, plan-pinned tasks, custom inspection forms, and offline-first data capture — all accessible from the field and synced to the office in real time.

On the plan, installers create a task at each penetration, select the application location and firestop system from dropdown menus, work through the process steps, and assign the task back to the office for approval.

For the physical tag, users have two options: a Hilti firestop identification label affixed at the seal, or a QR code generated per firestop task in Fieldwire, printed, and attached to the penetration. Fieldwire can export QR codes from Plans or Tasks in PDF format for label printing. During inspection, scanning that code from a phone opens the task and the full detail of what was installed.

Photos go straight on to the task. Crews can take photos directly from the app, and photo stamps can automatically display date, time, and GPS coordinates in reports and form exports. Custom inspection forms standardise data collection across every inspection.

Because the seal often goes in where there is no signal, the app works fully offline: crews complete inspections, take photos, and drop pins, and everything syncs automatically once a connection returns. At completion, a report detailing all firestop locations, systems, and expansion joints can be handed to the owner.

Ogilvie Fire Protection, which has delivered structural and passive fire safety services across the UK and Ireland since 2015, has used Fieldwire since its first year. The business uses Fieldwire to record every action and every item required as part of running a fire protection business, including checklists, daily reports, and documentation. Ogilvie reports saving up to £25,000 per year and credits Fieldwire as part of achieving ISO 9001 certification.

Fieldwire gives field teams and the office a shared, real-time view of every firestop task, photo, and inspection, so the evidence that proves compliance is built as the work goes in.

Keep a defensible record of every seal

Firestopping documentation proves a building is safe and that the work was done right. On higher-risk buildings, missing golden-thread information can put sign-off at risk, leading to delays, costs and fractured relationships with clients. The contractors who manage this well capture the tested system, the location, the photos, the installer, and the sign-off as the seal goes in — on the plan, in one place, ready to export.

Start for free with Fieldwire

Frequently asked questions about firestopping documentation requirements

For higher-risk buildings in England under the Building Safety Act 2022 framework, firestopping records may form part of the golden thread and commonly include the tested system reference or certification, the products used with batch traceability, the penetration location, photographs taken before close-in and of the completed installation, the installer's identity and qualifications, and the date of installation. For these buildings, the records must be kept digitally.

The statutory digital golden thread applies specifically to higher-risk buildings, defined as at least 18 metres tall or seven storeys with at least two residential units. However, firestopping in all buildings still needs traceable evidence that installations match tested specifications and that passive fire safety information is properly handed over.

The record should confirm both product certification and installer certification separately. Products should carry third-party certification backed by test evidence such as BS EN 1366-3:2021+A1:2024. The installer company should hold third-party certification under a UKAS-accredited scheme — FIRAS, LPCB, and IFC are the main routes in the UK. Recording both makes clear that the right product was used and that a competent company fitted it.

Jake Ogden

Jake started his career as a Civil Engineer in the UK, working on school, hotel, and heritage refurbishment projects with Kier Construction. He now brings that hands-on construction experience to his role at Fieldwire, helping clients implement digital tools to streamline workflows, improve productivity, and get the most out of the platform.

Get started now

Field service management software for construction

4,000,000+ projects worldwide

Helping the largest construction companies in the world more easily manage their job sites.

Graham UKEllisDonClark ConstructionBuiltClimatec logoBrookfieldCougnaudWebcorJohnson ControlsMorguardBockmon & WoodySutter HealthColt BuildersSpeller MetcalfeGraham